Waterline Replacement/Upgrading

Port au Port West-Aguathuna-Felix Cove, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$157,810
Federal share50%

of $315.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
Sep 5, 2017(actual)
Construction end
Nov 24, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 1, 2017
  • Construction end3 months lateforecast Aug 31, 2017

Also in Port au Port West-Aguathuna-Felix Cove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47079 in the federal list. How to read these figures.