Waterline Replacement/Upgrading
Port au Port West-Aguathuna-Felix Cove, Newfoundland and Labrador
Federal contribution
$157,810
Federal share50%
of $315.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Port au Port West-Aguathuna-Felix Cove
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Nov 24, 2017(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 1, 2017
- Construction end3 months lateforecast Aug 31, 2017
Also in Port au Port West-Aguathuna-Felix Cove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47079 in the federal list. How to read these figures.