Back to projects

Water Main Replacement – Town of Port au Port West-Aguathuna-Felix Cove

Port au Port West-Aguathuna-Felix Cove, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$250,601
Federal share40%

of $626.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2020
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 24, 2020(actual)
Construction end
Oct 23, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 30, 2020