Water Tower Construction
Federal contribution
$553,034
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2008
20082009201020112012
Built
Approved 7 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Oromocto
- Construction start
- Aug 31, 2007(actual)
- Construction end
- Mar 23, 2012(actual)
Against the original forecast
- Construction start2 months earlyforecast Nov 1, 2007
- Construction end4.1 years lateforecast Jan 31, 2008
Also in Oromocto