Route 7 - Rockwell Stream to Brizley Stream
Federal contribution
$580,000
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built
Approved 14 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- May 3, 2010(actual)
- Construction end
- May 27, 2010(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 31, 2010
- Construction end2 months earlyforecast Jul 31, 2010
Also in Oromocto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34958 in the federal list. How to read these figures.