Watermain Renewal - Restigouche Road and Nasson Crescent

Oromocto, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$500,805
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Oromocto
Construction start
May 1, 2017(actual)
Construction end
Nov 30, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 1, 2017
  • Construction end4 weeks lateforecast Oct 31, 2017

Also in Oromocto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48226 in the federal list. How to read these figures.