Onandaga Street - Oromocto

Oromocto, New Brunswick

completeWastewaterCVRIS
Federal contribution
$958,540
Federal share80%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2021
2021
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Oromocto
Construction start
Jun 1, 2021(actual)
Construction end
Sep 8, 2021(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 17, 2021
  • Construction end4 months earlyforecast Dec 31, 2021

Also in Oromocto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57977 in the federal list. How to read these figures.