Water Treatment Plant Upgrade - Fort Smith

Fort Smith, Northwest Territories

completeDrinking WaterMRIF
Federal contribution
$360,000
Federal share29%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20072009201120132015
Built

Approved 9.5 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Fort Smith
Construction start
Sep 26, 2006(actual)
Construction end
Mar 21, 2012(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 1, 2006
  • Construction end4.2 years lateforecast Dec 31, 2007