Replacement of Bridge #13
Federal contribution
$128,471
Federal share33%
of $385.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
2007200820092010
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Chisholm
- Construction start
- Oct 1, 2007(actual)
- Construction end
- Dec 31, 2009(actual)
Also in Chisholm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16052 in the federal list. How to read these figures.