Landfill Site - Groundwater Monitoring Wells

Chisholm, Ontario

completeSolid Waste ManagementISF
Federal contribution
$17,118
Federal share32%

of $54.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Chisholm
Construction start
Jun 6, 2009(actual)
Construction end
Aug 13, 2010(actual)

Against the original forecast

  • Construction end4 months lateforecast Mar 31, 2010