Alderdale Road Reconstruction

Chisholm, Ontario

completeHighways and RoadsRNIS
Federal contribution
$1.6M
$1,557,642
Federal share60%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2020
2021
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of Chisholm
Construction start
Jul 23, 2020(actual)
Construction end
Nov 9, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 29, 2020
  • Construction end14 months lateforecast Sep 4, 2020