Public Works Building Safety Retrofit
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Chisholm
- Construction start
- Sep 1, 2022(actual)
- Construction end
- Mar 10, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Dec 30, 2022
Also in Chisholm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59559 in the federal list. How to read these figures.