Lagoon Expansion

Big River, Saskatchewan

completeWastewaterMRIF
Federal contribution
$250,000
Federal share24%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
200720082009201020112012
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Big River
Construction start
Dec 20, 2006(actual)
Construction end
Dec 6, 2011(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2012