Town of Big River - Rink and Community Centre Revitalization

Big River, Saskatchewan

completeRecreationRNIS
Federal contribution
$405,942
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 6, 2022
202320242025
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Big River
Construction start
Jul 13, 2023(actual)
Construction end
Aug 14, 2025(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 15, 2023
  • Construction end4 months lateforecast Mar 31, 2025

Also in Big River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63896 in the federal list. How to read these figures.