Pickerel Point Road Construction

Big River, Saskatchewan

completeHighways and RoadsCC Top Up
Federal contribution
$164,369
Federal share33%

of $493.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Feb 10, 2010(actual)
Construction end
Oct 11, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast May 1, 2010
  • Construction end3 weeks earlyforecast Oct 31, 2011

Also in Big River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26350 in the federal list. How to read these figures.