Sewage Lift Station Generator and Force Main

Big River, Saskatchewan

completeWastewaterCC
Federal contribution
$200,000
Federal share33%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Big River
Construction start
Oct 28, 2009(actual)
Construction end
Sep 6, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2009
  • Construction end7 months earlyforecast Mar 31, 2012

Also in Big River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22307 in the federal list. How to read these figures.