Tr'inke Zho Centre Playground
Federal contribution
$66,874
Federal share30%
of $225.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 18, 2007
20062007200820092010
Built
Approved 11 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- First Nations of Tr'Ondek Hwech'In
- Construction start
- Jan 15, 2008(actual)
- Construction end
- Jan 31, 2010(actual)
Against the original forecast
- Construction start16 months lateforecast Aug 31, 2006
- Construction end2.5 years lateforecast Jul 31, 2007
Also in Dawson City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16366 in the federal list. How to read these figures.