Back to projects

Replacement of Lee Valley Road Culverts #12 and #14

Massey, Ontario

completeHighways and RoadsMRIF
Federal contribution
$159,307
Federal share33%

of $477.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
200720082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 1, 2007(actual)
Construction end
Dec 4, 2008(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 1, 2006
  • Construction end13 months lateforecast Oct 31, 2007

Also in Massey