Realignment and reconstruction of Birch Lake Road
Federal contribution
$237,077
Federal share33%
of $711.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Sables-Spanish Rivers
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Jun 1, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2009
- Construction end4 months earlyforecast Sep 30, 2010
Also in Massey