Public Works Building Renovation and Addition
Federal contribution
$131,000
Federal share33%
of $393.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Sables-Spanish Rivers
- Construction start
- Jul 13, 2009(actual)
- Construction end
- Sep 17, 2010(actual)
Also in Massey