Back to projects

Public Works Building Renovation and Addition

Massey, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$131,000
Federal share33%

of $393.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 13, 2009(actual)
Construction end
Sep 17, 2010(actual)

Also in Massey

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30378 in the federal list. How to read these figures.