Back to projects

Sables-Spanish Rivers Asset Management

Massey, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,343
Federal share33%

of $13.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 24, 2007
2007200820092010
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 1, 2007(actual)
Construction end
Oct 31, 2010(actual)

Also in Massey

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17357 in the federal list. How to read these figures.