Upgrade of the Stirling Sewage Lagoon
Federal contribution
$303,333
Federal share33%
of $910.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
200720082009
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Stirling-Rawdon
- Construction start
- Dec 22, 2006(actual)
- Construction end
- Mar 12, 2009(actual)
Against the original forecast
- Construction start4 months lateforecast Sep 1, 2006
- Construction end13 months lateforecast Jan 31, 2008
Also in Stirling
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16643 in the federal list. How to read these figures.