Rehabilitation of Front Street Sanitary Sewer System
Federal contribution
$665,373
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Stirling-Rawdon
- Construction start
- May 28, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction end10 months lateforecast Dec 31, 2010