Water Treatment Plant - Standy Power System

Stirling, Ontario

completeDrinking WaterISF
Federal contribution
$37,393
Federal share31%

of $120.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Stirling-Rawdon
Construction start
May 31, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 1, 2010
  • Construction end3 months earlyforecast Mar 31, 2011