Reconstruction of Hoards Road

Stirling, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$795,605
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Stirling-Rawdon
Construction start
Sep 3, 2009(actual)
Construction end
Oct 1, 2011(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 31, 2011