Reconstruction of Hoards Road
Federal contribution
$795,605
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Stirling-Rawdon
- Construction start
- Sep 3, 2009(actual)
- Construction end
- Oct 1, 2011(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Stirling
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27612 in the federal list. How to read these figures.