Water and Sewer Mains

Estevan, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$325,000
Federal share15%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
2007
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Estevan
Construction start
Jan 3, 2007(actual)
Construction end
Nov 21, 2007(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end4 months earlyforecast Mar 31, 2008

Also in Estevan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16807 in the federal list. How to read these figures.