Stoney Lake Water Line Upgrade-S.Humboldt Water Users Corp.

Humboldt, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$12,908
Federal share25%

of $51.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 28, 2007
20082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 24, 2007(actual)
Construction end
Jun 29, 2009(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2007
  • Construction end9 months earlyforecast Mar 31, 2010