Sewage Station Upgrade
Federal contribution
$23,050
Federal share25%
of $92.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 13, 2007
2007
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Humboldt
- Construction start
- Dec 20, 2006(actual)
- Construction end
- Nov 16, 2007(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 1, 2007
- Construction end4 months earlyforecast Mar 31, 2008
Also in Humboldt
- City of Humboldt - Wastewater Treatment System Upgrades$14.7M
- Water Distribution Plant and Reservoir$1.4M
- Uniplex and High School Retrofit$973.2K
- City of Humboldt Storm Water Detention Pond$647.1K
- Regional Authority of Carlton Trail Waste Management District (REACT) - Phase 2 Decommissioning of REACT Waste Management Facility$583.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16855 in the federal list. How to read these figures.