Sewage Station Upgrade

Humboldt, Saskatchewan

completeWastewaterMRIF
Federal contribution
$23,050
Federal share25%

of $92.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 13, 2007
2007
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Humboldt
Construction start
Dec 20, 2006(actual)
Construction end
Nov 16, 2007(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end4 months earlyforecast Mar 31, 2008

Also in Humboldt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16855 in the federal list. How to read these figures.