Township of Killaloe, Hagarty and Richards Asset Management Program
Killaloe, Hagarty and Richards, Ontario
Federal contribution
$3,754
Federal share33%
of $11.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedMay 4, 2007
20072008
Built
Approved 5 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Killaloe, Hagarty And Richards, Township of
- Construction start
- May 4, 2007(actual)
- Construction end
- Feb 12, 2008(actual)
Against the original forecast
- Construction end14 months earlyforecast Mar 31, 2009
Also in Killaloe, Hagarty and Richards
- Supervisory Control and Data Acquisition System Upgrade$65.0K
- Killaloe Wastewater Pollution Control Plant Raw Sewage Grinder System replacement$20.6K
- Stone Church Road and Cardinal Road Rehabilitation$19.8K
- Killaloe Wastewater Pollution Control Plant , Henry Street Pumping Station upgrades$17.5K
- Cameron Street Rehabilitation$14.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17325 in the federal list. How to read these figures.