Township of Chatsworth Asset Management
Federal contribution
$4,312
Federal share33%
of $12.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedMay 7, 2007
200720082009
Built
Approved 5 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Chatsworth
- Construction start
- Jun 1, 2007(actual)
- Construction end
- Mar 16, 2009(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Mar 31, 2009
Also in Chatsworth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17397 in the federal list. How to read these figures.