Chatsworth Road 24
Federal contribution
$166,666
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Chatsworth
- Construction start
- Jul 30, 2009(actual)
- Construction end
- Nov 9, 2009(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 1, 2009
- Construction end2 months lateforecast Aug 31, 2009
Also in Chatsworth
- Replacement of Gamble Bridge and Reconstruction of Sideroad 1$395.4K
- Williamsford Community Centre Rehabilitation$250.0K
- Concession 6$140.0K
- Replace existing water standpipe with a larger volume standpipe to meet water pressures, fire flows, and foster economic growth$50.0K
- Township of Chatsworth Asset Management$4.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30005 in the federal list. How to read these figures.