Williamsford Community Centre Rehabilitation

Chatsworth, Ontario

completeRecreationISF
Federal contribution
$250,000
Federal share33%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Chatsworth
Construction start
Apr 15, 2010(actual)
Construction end
Dec 7, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Feb 28, 2011