Concession 6
Federal contribution
$139,960
Federal share33%
of $420.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Chatsworth
- Construction start
- Aug 24, 2009(actual)
- Construction end
- Feb 4, 2010(actual)
Against the original forecast
- Construction end3 months lateforecast Nov 13, 2009
Also in Chatsworth
- Replacement of Gamble Bridge and Reconstruction of Sideroad 1$395.4K
- Williamsford Community Centre Rehabilitation$250.0K
- Chatsworth Road 24$166.7K
- Replace existing water standpipe with a larger volume standpipe to meet water pressures, fire flows, and foster economic growth$50.0K
- Township of Chatsworth Asset Management$4.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30006 in the federal list. How to read these figures.