Abbotsford - James Treatment Plant Bio Solids Dewatering
Federal contribution
$1.0M
$1,033,257
Federal share32%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2008
20082009201020112012
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Abbotsford
- Construction start
- Nov 19, 2007(actual)
- Construction end
- Mar 31, 2012(actual)
Also in Abbotsford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17543 in the federal list. How to read these figures.