Coquitlam - Poirier Library Renovation

Coquitlam, British Columbia

completeCultureMRIF
Federal contribution
$1.0M
$1,000,000
Federal share31%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2008
200820092010
Built

Approved 5 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Coquitlam
Construction start
Dec 12, 2007(actual)
Construction end
Mar 31, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Nov 19, 2007

Also in Coquitlam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17544 in the federal list. How to read these figures.