OMC4 Maintenance Facilities
Federal contribution
$94.7M
$94,730,000
Federal share40%
of $236.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
today
2022202420262028
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- TransLink
- Construction start
- Feb 16, 2023(actual)
- Construction end
- Jul 23, 2029(forecast)