Mundy Park Pool

Coquitlam, British Columbia

completeRecreationCCRIS
Federal contribution
$2.4M
$2,417,401
Federal share40%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022202320242025
Built
Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Coquitlam
Construction start
May 1, 2023(actual)
Construction end
Apr 15, 2025(actual)

Against the original forecast

  • Construction end4 months lateforecast Dec 2, 2024

Also in Coquitlam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61425 in the federal list. How to read these figures.