Mundy Park Pool
Federal contribution
$2.4M
$2,417,401
Federal share40%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022202320242025
Built
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Coquitlam
- Construction start
- May 1, 2023(actual)
- Construction end
- Apr 15, 2025(actual)
Against the original forecast
- Construction end4 months lateforecast Dec 2, 2024
Also in Coquitlam
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61425 in the federal list. How to read these figures.