Coquitlam - Lougheed Highway
Federal contribution
$5.9M
$5,945,957
Federal share32%
of $18.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 4, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 7 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Coquitlam
- Construction start
- Apr 26, 2010(actual)
- Construction end
- Oct 15, 2011(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 1, 2010
Also in Coquitlam
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39425 in the federal list. How to read these figures.