King Edward Street Improvements
Federal contribution
$2.5M
$2,466,667
Federal share33%
of $7.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Coquitlam
- Construction start
- Apr 15, 2010(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 31, 2011
Also in Coquitlam
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39120 in the federal list. How to read these figures.