East Courtenay Reservoir Twinning

Courtenay, British Columbia

completeDrinking WaterMRIF
Federal contribution
$1.3M
$1,333,333
Federal share30%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 4, 2008
20082009201020112012
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Dec 12, 2007(actual)
Construction end
May 30, 2012(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Nov 19, 2007
  • Construction end2 months lateforecast Mar 31, 2012

Also in Courtenay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17686 in the federal list. How to read these figures.