East Courtenay Reservoir Twinning
Federal contribution
$1.3M
$1,333,333
Federal share30%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 4, 2008
20082009201020112012
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Regional District of Comox Valley
- Construction start
- Dec 12, 2007(actual)
- Construction end
- May 30, 2012(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 19, 2007
- Construction end2 months lateforecast Mar 31, 2012
Also in Courtenay
- 6th Street Active Transportation Bridge in Courtenay, British Columbia$2.5M
- Courtenay - 17th Street Bike Lanes$1.4M
- Kus-kus-sum: Restoration of Estuarine Habitat to Re-establish Ecosystem Services and Build Coastal Resiliency$1.0M
- Rehabilitation of the 5th Street Bridge$982.5K
- Highway 19A - 17th Street Bridge Right Turn Lane$650.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17686 in the federal list. How to read these figures.