Kus-kus-sum: Restoration of Estuarine Habitat to Re-establish Ecosystem Services and Build Coastal Resiliency
Federal contribution
$1.0M
$1,000,000
Federal share78%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 10, 2025
today
20252026
BuiltForecast
Approved 12 months before the announcement.
- Program
- Natural Infrastructure Fund
- Ultimate recipient
- Comox Valley Project Watershed Society
- Construction start
- Aug 5, 2025(actual)
- Construction end
- Dec 1, 2026(forecast)
Against the original forecast
- Construction start2 weeks lateforecast Jul 21, 2025
Also in Courtenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65896 in the federal list. How to read these figures.