6th Street Active Transportation Bridge in Courtenay, British Columbia
Federal contribution
$2.5M
$2,502,231
Federal share51%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2024
2023202420252026
Built
Approved 16 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Courtenay
- Construction start
- Apr 1, 2025(actual)
- Construction end
- Jun 16, 2026(actual)
Against the original forecast
- Construction start16 months lateforecast Dec 4, 2023
- Construction end3 months earlyforecast Sep 30, 2026