Courtenay - 17th Street Bike Lanes
Federal contribution
$1.4M
$1,376,288
Federal share80%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Courtenay
- Construction start
- May 24, 2022(actual)
- Construction end
- Oct 17, 2022(actual)
Against the original forecast
- Construction end14 months earlyforecast Dec 30, 2023
Also in Courtenay
- 6th Street Active Transportation Bridge in Courtenay, British Columbia$2.5M
- East Courtenay Reservoir Twinning$1.3M
- Kus-kus-sum: Restoration of Estuarine Habitat to Re-establish Ecosystem Services and Build Coastal Resiliency$1.0M
- Rehabilitation of the 5th Street Bridge$982.5K
- Highway 19A - 17th Street Bridge Right Turn Lane$650.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60548 in the federal list. How to read these figures.