Back to projects

Municipality of Tweed Asset Management

Tweed, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,214
Federal share33%

of $12.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 24, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Tweed
Construction start
Jun 1, 2007(actual)
Construction end
Aug 27, 2009(actual)

Against the original forecast

  • Construction end5 months lateforecast Mar 31, 2009