Asset Management Program

Merrickville-Wolford, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,801
Federal share33%

of $11.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 7, 2007
200720082009
Built

Approved 5 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 1, 2007(actual)
Construction end
Mar 31, 2009(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Jan 31, 2009