Back to projects

Zone III Transmission Line & Reservoir Expansion

Grande Prairie, Alberta

completeDrinking WaterMRIF
Federal contribution
$2.4M
$2,408,516
Federal share33%

of $7.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 20, 2007
200820092010
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Grande Prairie
Construction start
Oct 9, 2007(actual)
Construction end
Oct 14, 2010(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2007

Also in Grande Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18470 in the federal list. How to read these figures.