Grande Prairie Emergency Response and Activity Center
Federal contribution
$3.2M
$3,200,000
Federal share80%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 17, 2021
2022
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Grande Prairie
- Construction start
- Apr 19, 2021(actual)
- Construction end
- Jan 10, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast Mar 1, 2021
- Construction end8 weeks lateforecast Nov 15, 2021
Also in Grande Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58877 in the federal list. How to read these figures.