Paving Highway 43

Grande Prairie, Alberta

completeHighways and RoadsISF
Federal contribution
$9.1M
$9,081,557
Federal share50%

of $18.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 2, 2009
ApprovedJul 23, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 1, 2009(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Grande Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28467 in the federal list. How to read these figures.