Schedule
Announced and approvedNov 16, 2012
2013201420152016
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Aquatera Utilities Inc.
- Construction start
- Feb 4, 2013(actual)
- Construction end
- Jan 18, 2016(actual)
Against the original forecast
- Construction start3 months lateforecast Oct 31, 2012
- Construction end3 weeks lateforecast Dec 31, 2015