Grande Prairie Wastewater Treatment Plant Phase II Upgrades

Grande Prairie, Alberta

completeWastewaterMIC
Federal contribution
$10.0M
$10,000,000
Federal share19%

of $52.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 16, 2012
2013201420152016
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
Aquatera Utilities Inc.
Construction start
Feb 4, 2013(actual)
Construction end
Jan 18, 2016(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 31, 2012
  • Construction end3 weeks lateforecast Dec 31, 2015