Trinity-Placentia Stadium - Renovations and Expansion

Whitbourne, Newfoundland and Labrador

completeRecreationMRIF
Federal contribution
$193,633
Federal share30%

of $651.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 23, 2009(actual)
Construction end
Mar 31, 2013(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2009
  • Construction end3 years lateforecast Mar 31, 2010

Also in Whitbourne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18663 in the federal list. How to read these figures.