Watermain Repairs & Upgrades With Flush Valve
Whitbourne, Newfoundland and Labrador
Federal contribution
$1.2M
$1,207,379
Federal share40%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2026
202420252026
Built
Approved 2.8 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Whitbourne
- Construction start
- Jun 3, 2024(actual)
- Construction end
- Jan 27, 2025(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2024
- Construction end3 months earlyforecast May 8, 2025
Also in Whitbourne
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67331 in the federal list. How to read these figures.